Remote Community Road Upgrades in Cape York

Funding Program:Nation Building Program Off-Network
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Mid 2009 - 2012
Estimated Project Cost:$21,000,000
Australian Government Contribution:$10,500,000
State:QLD

Project Description

This project will deliver sealed roads, gravel road and improving creek crossings to remote communities in Cape York, such as the Lockhart River Community Access Road upgrade.

Six roads have been identified under the program including:

Benefits

The benefits of this project are:

  • A reduction in the frequency and length of the periodic road closures which isolate indigenous communities and through traffic;
    a reduction in transport operation costs;
  • improvement of road conditions and regional access through upgraded construction to a sealed standard;
  • the safe operation of transport vehicles within a traffic stream dominated by local indigenous and tourist vehicles; and
  • consistent driving conditions, through improved stream crossings, dust elimination, better road alignment and improved visibility.

Funding

The Australian Government has committed $10.5 million to the project, in partnership with the Queensland Government.

Timetable

The Works commenced on the first of the projects, Lockhart River Community Access Road, mid 2009.  The remaining works will be carried out progressively to 2012.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 13/01/2010